Gather Update 1.7.21
The continued above-normal temperatures we had before Christmas was a huge advantage for the crew as they worked to complete the cement flat work. To date, 90% of the flat work is done and 20% of the ramp is poured. The laminated beams and decking for the floors and ceiling were delivered this week and in the next few weeks, the crew will be putting up walls and setting beams. And if weather permits, the ramp will be poured before the roof is installed.
Thank you for keeping this project and the building crew in your prayers.